Capital Projects: Phase B

Overview

A host of technology improvements are required in order to support the communication services that will be made available once the capital construction is complete. These improvements are being made via a number of technology projects which include enabling Voice over IP technology, enabling Video over IP technology, enabling enhanced 911 services, developing prototypes for in-building distributed antenna systems, stabilizing the existing infrastructure so it is maintainable over the construction period, decommissioning aging and unused services in the residence halls, and documenting the physical plant and building structures in a way that supports the capital construction.

Facilities served by Phase B include those buildings that are served by ADFs (Area Distribution Systems) in Interdisciplinary Science Building, Social Sciences and Communications. A building list for Phase B can be found in the table below:


Phase B Building List

Click on the building title for more details.

7171        Astronomy A
  • Telecomm Cabinet installation start/end date: 6/30/16-7/11/16
  • Cable installation tentative start /end dates: 5/11/16-7/29/16
  • VoIP deployment start date: 8/11/16
7172        Astronomy B
  • Telecomm Cabinet installation start/end date: 6/30/16-7/11/16
  • Cable installation tentative start /end dates: 5/11/16-7/29/16
  • VoIP deployment start date: 8/11/16
7947        Biomedical Sciences
  • VoIP deployment start date: 8/2016
7693        Center for Adaptive Optics
  • Telecomm Room renovation/upgrade (Rm. 118a) start/end dates: 2/16-5/31/16.
  • Cable installation start/end dates: 6/6/16-7/29/2016
  • VoIP deployment tentative start date: TBD
7146        Central Heat Plant
  • Cable installation start/end dates: 4/16-7/12/16
  • VoIP deployment start date: 8/16/16
7816        Central Heat Plant Trailer 1
  • Telecomm Room renovation/upgrade tentative start/end date: 7/05/16-7/29/16-
  • Cable installation tentative start /end dates: 8/1/16-8/5/16
  • VoIP deployment tentative start date: TBD
7939        Central Heat Plant 2
  • Cable installation tentative start/end dates: 7/18/16-7/22/16
  • VoIP deployment start date: 8/12/16
7911        College Nine Apartment Building 1
  • Outside Plant Fiber Installation tentative start/end dates: 6/13/16-9/14/16
7912        College Nine Apartment Building 2
  • Outside Plant Fiber Installation tentative start/end dates: 6/13/16-9/14/16
7913        College Nine Apartment Building 3
  • Outside Plant Fiber Installation tentative start/end dates: 6/13/16-9/14/16
7914        College Nine Apartment Building 4
  • Outside Plant Fiber Installation tentative start /end dates: 6/13/16-9/14/16
7915        College Nine Apartment Building 5
  • Outside Plant Fiber Installation tentative start/end dates: 6/13/16-9/14/16
7917        College Nine Commons
  • Telecomm Room renovation/upgrade tentative start date: 9/12/16
  • Outside Plant Fiber Installation tentative start/end dates: 6/13/16-9/14/16
7930        College Nine Res Hall Lounge (Namaste)
  • Telecomm Room renovation/upgrade tentative start date: 9/12/16
  • Cable installation tentative start /end dates: 9/26/16-10/14/16
7931        College Nine Residential Hall 1
  • Outside Plant Fiber Installation tentative start /end dates: 6/13/16-9/14/16
7932        College Nine Residential Hall 2
  • Outside Plant Fiber Installation tentative start /end dates: 6/13/16-9/14/16
7933        College Nine Dining Hall
  • Telecomm Room renovation/upgrade tentative start date: 6/2016-7/29/16
  • Cable installation tentative start /end dates: 8/3/16-8/31/16
  • VoIP deployment tentative start date: TBD
7934        College Nine Residential Hall 3
  • Outside Plant Fiber Installation tentative start/end dates: 6/13/16-9/14/16
7936        College Ten Residential Hall 4
  • Outside Plant Fiber Installation tentative start/end dates: 6/13/16-9/14/16
7937        College Ten Residential Hall 5
  • Outside Plant Fiber Installation tentative start /end dates: 6/13/16-9/14/16
7938        College Ten Residential Hall 6
  • Outside Plant Fiber Installation tentative start/end dates: 6/13/16-9/14/16
7200        Cowell Student Health Center
  • WAP installation start/end dates: 7/19/16-7/21/16
  • VoIP deployment tentative start date: 8/30-31/16
7201        Cowell Student Health Center Addition
  • WAP installation start/end dates: 7/19/16-7/21/16
  • VoIP deployment tentative start date: 8/30-31/16
7175        Communications Building
  • Telecomm Room renovation/upgrade tentative start/end date: 5/2/16-7/29/16
  • Cable installation tentative start/end dates: 04/1/16-7/12/16
  • Partial VoIP deployment start/end dates: 1st and 2nd floors: 6/27/16-6/29/16, remaining VoIP deployment will begin 8/2016
7529        Communications Trailer 1
  • Telecomm Room renovation/upgrade tentative tentative start/end date: Nov/Dec 2016
  • Cable installation tentative start /end dates: December 2016
  • VoIP deployment tentative start date: TBD
7727        Communications Trailer 2
  • Telecomm Room renovation/upgrade tentative tentative start/end date: Nov/Dec 2016
  • Cable installation tentative start /end dates: December 2016
  • VoIP deployment tentative start date: TBD
7487        Communications Trailer 3
  • Telecomm Room renovation/upgrade tentative tentative start/end date: Nov/Dec 2016
  • Cable installation tentative start /end dates: December 2016
  • VoIP deployment tentative start date: TBD
7775        Earth and Marine Sciences
  • Telecomm Room renovation/upgrade start/end date: 02/16-05/31//16
  • Cable installation tentative start /end dates: 7/11/16-8/31/16
  • VoIP deployment tentative start date: TBD
7940        Engineering 2
  • Wireless Access Point (WAP) installation start/end dates: 5/2016-7/22/16
  • VoIP deployment tentative start date: TBD
7813        Environmental Health & Safety Trailer
  • Telecomm Room renovation/upgrade tentative start/end date: 9/12/16
  • Cable installation tentative start /end dates: 9/26/16-10/14/16
  • VoIP deployment tentative start date: TBD
7098        Interdisciplinary Sciences Bldg
  • Telecomm Room renovation/upgrade start/end dates: 2/15-7/22/16 (Rm. 103)
  • Rooms Affected: 103, 103a, 105, 390b
  • Cable installation start /end dates: 4th floor: 5/16/16-5/19/16
  • Cable installation start /end dates: 3rd floor: 5/20/16-5/25/16
  • Cable installation start /end dates: 2nd floor: 5/26/16-5/30/16
  • Cable installation start /end dates: 1st floor: 5/31/16-6/3/16
  • VoIP deployment start/end dates: 4th and 5th floor: 6/4-5/16
  • VoIP deployment start/end dates: 3rd floor: 6/17/16
  • VoIP deployment start/end dates: 1st and 2nd floor: 6/22/16
  • VoIP deployment start/end dates: 2nd floor: 6/23/16
7194        Jack Baskin Engineering
  • Telecomm Room construction start/end dates: December 2015-7/22/16
  • Rooms Affected: 091a, 075a, TR1a, TR1b, 261B, TR2a, TR2b, TR3a, TR3b
  • Cable installation tentative start /end dates: 5/01/16- tentative-8/26/2016
  • VoIP deployment tentative start date: 1st Floor 9/19-21st- excluding PSB wing.
7942        Jack Baskin Engineering Auditorium
  • Telecomm Room renovation/upgrade start/end date: TBD
  • Rooms Affected: a168, a310, a410, c201, c301, b302, c401, c501
  • Cable installation tentative start /end dates: 7/1/16-9/23/16
  • VoIP deployment tentative start date: TBD
7180        Nat Sci 2 Annex
  • Telecomm Room renovation/upgrade start/end dates: 7/16-TBD
  • Cable installation start /end dates: 7/18/16-TBD
  • VoIP deployment tentative start date: TBD
7179        Natural Science 2
  • Telecomm Room renovation/upgrade tentative start/end dates: 12/11/15-7/18/16-tentative
  • Cable installation start/end dates: 7/21-8/19/16
  • 4th floor cable installation start/end dates: 7/21-7/27/16
  • 3rd floor cable installation start/end dates: 7/28-8/4/16
  • 2nd floor Cable installation start/end dates: 8/8-8/12/16
  • 1st floor cable installation start/end dates: 8/15-8/19/16
  • VoIP deployment tentative start date: TBD
7481        Nat Sci Paleo-Magnetic Lab
  • Telecomm Room renovation/upgrade tentative start date: 5/8/16-7/15/16
  • Cable installation tentative start/end dates: 7/11-15/16
  • VoIP deployment start date:TBD
7783        Nat Sci Woodshop
  • Telecomm Room renovation/upgrade tentative start date: 5/8/16
  • Cable installation tentative start/end dates: 7/11-15/16
  • VoIP deployment start date:TBD
7782        Science & Engineering Library
  • Telecomm Room renovation/upgrade start/end dates: 1/16-4/8/16
  • Cable installation tentative start/end dates: 2/16/16-4/20/16
  • VoIP deployment tentative start/end dates: 5/3/2016-5/6/16-COMPLETED
7920        Social Sciences 1
  • Telecomm Room renovation/upgrade start/end date: January 2016-5/13/16
  • Rooms Affected: 004, 158, 262, 362, 458
  • Cable installation start/end dates: 4/4/16-5/20/16
  • VoIP deployment tentative start date: 5/6/16-5/20/16
7921        Social Sciences 2
  • Telecomm Room renovation/upgrade start/end dates: 2/16-4/15/16
  • Rooms Affected: 016, 118, 134, 218, 234, 318, 334, 434
  • Cable installation tentative start /end dates: 7/18/16-TBD
  • VoIP deployment start date: 3rd Floor on 9/12
  • VoIP deployment start date: 4th Floor on 9/14