Capital Projects: Phase B

Overview

A host of technology improvements are required in order to support the communication services that will be made available once the capital construction is complete. These improvements are being made via a number of technology projects which include enabling Voice over IP technology, enabling Video over IP technology, enabling enhanced 911 services, developing prototypes for in-building distributed antenna systems, stabilizing the existing infrastructure so it is maintainable over the construction period, decommissioning aging and unused services in the residence halls, and documenting the physical plant and building structures in a way that supports the capital construction.

Facilities served by Phase B include those buildings that are served by ADFs (Area Distribution Systems) in Interdisciplinary Science Building, Social Sciences and Communications. A building list for Phase B can be found in the table below:


Phase B Building List

Click on the building title for more details.

7171        Astronomy A
  • Telecomm Cabinet installation: COMPLETED
  • Cable installation: COMPLETED
  • VoIP deployment: COMPLETED
7172        Astronomy B
  • Telecomm Cabinet installation: COMPLETED
  • Cable installation: COMPLETED
  • VoIP deployment: COMPLETED
7947        Biomedical Sciences
  • VoIP deployment: COMPLETED
7693        Center for Adaptive Optics
  • Telecomm Room renovation/upgrade: COMPLETED
  • Cable installation: COMPLETED
  • VoIP deployment: COMPLETED
7146        Central Heat Plant
  • Cable installation: COMPLETED
  • VoIP deployment: COMPLETED
7816        Central Heat Plant Trailer 1
  • Telecomm Room renovation/upgrade: COMPLETED
  • Cable installation: COMPLETED
  • VoIP deployment: COMPLETED
7939        Central Heat Plant 2
  • Cable installation: COMPLETED
  • VoIP deployment: COMPLETED
7911        College Nine Apartment Building 1
  • Outside Plant Fiber Installation: COMPLETED
7912        College Nine Apartment Building 2
  • Outside Plant Fiber Installation: COMPLETED
7913        College Nine Apartment Building 3
  • Outside Plant Fiber Installation: COMPLETED
7914        College Nine Apartment Building 4
  • Outside Plant Fiber Installation: COMPLETED
7915        College Nine Apartment Building 5
  • Outside Plant Fiber Installation: COMPLETED
7917        College Nine Commons
  • Telecomm Room renovation/upgrade: COMPLETED
  • Outside Plant Fiber Installation tentative: COMPLETED
7930        College Nine Res Hall Lounge (Namaste)
  • Telecomm Room renovation/upgrade: COMPLETED
  • Cable installation: COMPLETED
7931        College Nine Residential Hall 1
  • Outside Plant Fiber Installation: COMPLETED
7932        College Nine Residential Hall 2
  • Outside Plant Fiber Installation: COMPLETED
7933        College Nine Dining Hall
  • Telecomm Room renovation/upgrade: COMPLETED
  • Cable installation: COMPLETED
  • VoIP deployment: COMPLETED
7934        College Nine Residential Hall 3
  • Outside Plant Fiber Installation: COMPLETED
7200        Cowell Student Health Center
  • WAP installation: COMPLETED
  • VoIP deployment: COMPLETED
7201        Cowell Student Health Center Addition
  • WAP installation: COMPLETED
  • VoIP deployment: COMPLETED
7175        Communications Building
  • Telecomm Room renovation/upgrade : COMPLETED
  • Cable installation: COMPLETED
  • Partial VoIP deployment: COMPLETED
7529        Communications Trailer 1
  • Upgrade removed from scope of work
7727        Communications Trailer 2
  • Upgrade removed from scope of work
7487        Communications Trailer 3
  • Telecomm Room renovation/upgrade: COMPLETED
  • Cable installation: COMPLETED
  • VoIP deployment: COMPLETED
7775        Earth and Marine Sciences
  • Telecomm Room renovation/upgrade: COMPLETED
  • Cable installation: COMPLETED
  • VoIP deployment: COMPLETED
7940        Engineering 2
  • Wireless Access Point (WAP) installation: COMPLETED
  • VoIP deployment: COMPLETED
7813        Environmental Health & Safety Trailer
  • Telecomm Room renovation/upgrade: COMPLETED
  • Cable installation: COMPLETED
  • VoIP deployment: COMPLETED
7098        Interdisciplinary Sciences Bldg
  • Telecomm Room renovation/upgrade: COMPLETED
  • Cable installation: COMPLETED
  • VoIP deployment: COMPLETED
7194        Jack Baskin Engineering
  • Telecomm Room construction: COMPLETED
  • Cable installation: COMPLETED
  • VoIP deployment: COMPLETED
7942        Jack Baskin Engineering Auditorium
  • Telecomm Room renovation/upgrade: COMPLETED
  • Cable installation: COMPLETED
  • VoIP deployment: COMPLETED
7936        John R. Lewis College
  • Outside Plant Fiber Installation: COMPLETED
7937        John R. Lewis College
  • Outside Plant Fiber Installation: COMPLETED
7938        John R. Lewis College
  • Outside Plant Fiber Installation: COMPLETED
7180        Nat Sci 2 Annex
  • Telecomm Room renovation/upgrade: COMPLETED
  • Cable installation: COMPLETED
  • VoIP deployment: COMPLETED
7179        Natural Science 2
  • Telecomm Room renovation/upgrade: COMPLETED
  • Cable installation: COMPLETED
  • VoIP deployment: COMPLETED
7481        Nat Sci Paleo-Magnetic Lab
  • Telecomm Room renovation/upgrade: COMPLETED
  • Cable installation: COMPLETED
  • VoIP deployment: COMPLETED
7783        Nat Sci Woodshop
  • Telecomm Room renovation/upgrade: COMPLETED
  • Cable installation: COMPLETED
  • VoIP deployment: COMPLETED
7782        Science & Engineering Library
  • Telecomm Room renovation/upgrade: COMPLETED
  • Cable installation: COMPLETED
  • VoIP deployment: COMPLETED
7920        Social Sciences 1
  • Telecomm Room renovation/upgrade: COMPLETED
  • VoIP deployment: COMPLETED
7921        Social Sciences 2
  • Telecomm Room renovation/upgrade: COMPLETED
  • Cable installation: COMPLETED
  • VoIP deployment: COMPLETED